Meadow Lark school ready for first day of class, despite continuing construction

Meadow Lark Elementary School
Teresa Sprague
Posted
and last updated

With the start of the 2023-2024 school year right around the corner, improvements are being made to Meadow Lark Elementary School in Great Falls.

Last spring, construction began to add four new classrooms - two primary and two upper-level intermediate rooms - as well as a storage space to the school.

The additions should help accommodate the growing number of students attending school in the Fox Farm area of Great Falls.

Teresa Sprague, the principal, explained, “They will be doing the majority of their work and the inside work during the school year. We are actually on track for where we plan for them to be. Construction should end in mid-November and we're looking forward to that."

Sprague also said construction will be loud at times, but the staff and the members of the construction team are doing everything possible to minimize the noise.

Meadow Lark school ready for first day of class, despite continuing construction
Meadow Lark school ready for first day of class, despite continuing construction

Safety continues to be the school’s top priority and plans are already in place for the upcoming year. Barricades have been put up as well as areas of the school have been blocked off.

With roughly 540 students attending Meadow Lark, teachers are ready for the additional space.

“It definitely will benefit the kids. We won't be standing on top of each other in the classroom, it'll be great, and it'll be nice to have some space to maybe do some small groups,” said second-grade teacher Billi Bergman.

For any parents with doubts, Sprague said, “I would just say to everybody that it looks like we're not going to be ready, but we are ready, and this is just what we've planned for. We look forward to having a great school year.”

The first day of class for Great Falls Public Schools is Wednesday, August 30, 2023.



TRENDING



(MARCH 31, 2022) Walking through the halls at Meadow Lark Elementary School on Fox Farm Road in Great Falls, you may not immediately feel like the school is overcrowded - but teachers and staff will tell you it definitely is. Compounding the problem is a large kindergarten class, so the district has decided to try to add more classrooms.

Ruth Uecker, Great Falls Public Schools Elementary Assistant Superintendent, is happy to explain the planned development at the school. “Our proposed expansion will be to add two additional classrooms at the end of this wing,” she said as she walked down the wing.

The expansion will require a reconfiguration of the school playground.

“The additional square footage will go out on a portion of this playground but we can reconfigure what’s out here and allow for space,” said Uecker, standing in the doorway leading from the school out to the playground.

She believes the overcrowding is due to the school being located in a part of the city experiencing growth.

"You can see that growth out south of Great Falls. It continues to have a lot of construction in that area,” Uecker said. “We’ve tried to limit the number of students in this building, so we do not take permissive transfers. Only the kids that live in in the Meadow Lark attendance area can attend this school.”

Boundary readjustments have also been considered as a way to try to alleviate overcrowding.

“That process landed us to where we kept the boundaries as is because it really doesn’t make sense to bus kids past their neighborhood school to another school,” Uecker explained.

Principal Teresa Sprague says the limited space has forced teachers and staff to get creative.

"We're always looking for, 'Where could we have this group meet?' or sometimes they're using the lounge or they're using the space over here by the pop machine and they're sitting on the floor,” said Sprague.

Storage space is also an issue.

"Places where we can put chairs and things like that because we often times have to move those things,” Sprague explained. “With all these kids coming in for kindergarten registration coming up and our kindergarten class this year having 96 students, we know that they’re just going to grow and get bigger and we’re going to welcome that extra space for sure."

The addition of classrooms isn't the only work planned at the school, though. A computer lab is going to be converted.

"We are going to need to remodel this space and turn it into an additional classroom for the fall of this next school year,” said Uecker.

A move that may seem small compared to the rest of the plan, but a move that could prove to be a big help.

She said the district recently received a bid for the work to construct the additional classrooms but it was more than what the district can afford.

As of Thursday, the school district hoped to put the project back out to bid in the fall and have the classrooms ready to go in 2023.

If the bids in the fall are still over budget, Uecker said the district will cross that bridge at that time.

“It’s all part of the process. We know what we have for a budget and what we have to work with. If that happens, then we will put our heads down and figure out what we can do to respond to that,” Uecker said.

When asked if the district is worried the overcrowding could eventually lead to overcrowding at middle and high schools when the students at Meadow Lark get there, Uecker said that was not a concern at the time because although Meadow Lark is overcrowded, the overall enrollment in Great Falls Public Schools is stable.